Remodel Week 9

Posted by Daniel Israel on Friday, September 18th, 2020 with Comments Off on Remodel Week 9

Greetings again to members, friends, and family of EBJI! It’s week 9 and we’re deep into construction! Finally we have some pictures that aren’t primarily of demolition and preparation! Our front entryway. It’s actually a slight ramp to allow wheelchair accessibility. This is front view of what used to be the entry to the office....

More

Remodel Week 8

Posted by Daniel Israel on Monday, September 14th, 2020 with Comments Off on Remodel Week 8

Greetings again to members, friends, and family of EBJI! Here we are, 8 weeks in. We hit a milestone, we finally poured concrete! It happened early in the morning, so I didn’t get to take pictures, one of the guys took a few pictures for me. I haven’t actually been inside since the pour, so...

More

Remodel Week 7

Posted by Daniel Israel on Thursday, September 3rd, 2020 with Comments Off on Remodel Week 7

Greetings again to members, friends, and family of EBJI! Here we are at the end of week 7. I missed last week, there was too much going on. There were a few schedule changes, but shortly before I arrived to take pictures, the city inspector was on site and and gave us the OK to...

More

Remodel Week 5

Posted by Daniel Israel on Tuesday, August 25th, 2020 with Comments Off on Remodel Week 5

Greetings again to members, friends, and family of EBJI! Here we are at the end of week 5. We can see more of the preparation taking place. I am told that the current plan is to pour the concrete this week if they can get the city inspectors in there to give the OK. Once...

More

Remodel Week 4

Posted by Daniel Israel on Sunday, August 16th, 2020 with Comments Off on Remodel Week 4

Greetings again to members, friends, and family of EBJI! Here we are at the end of week 4 of our remodel! The demolition is pretty much done and we can see more of the preparation taking place. When I stopped by there were a couple of guys using a wheelbarrow to remove dirt from the...

More

Remodel Week 3

Posted by Daniel Israel on Friday, August 7th, 2020 with Comments Off on Remodel Week 3

Greetings again to members, friends, and family of EBJI! Here we are at the end of week 3 of our remodel! The majority is still demolition, but we can see more of the preparation for the earthquake retrofit coming together. There’s been a lot of work on the floors, removing the flooring and prepping for...

More

Remodel Week 2

Posted by Daniel Israel on Monday, August 3rd, 2020 with Comments Off on Remodel Week 2

Greetings again to members, friends, and family of EBJI! Here we are at the end of week 2 of our remodel! As to be expected, the majority of the work is still demolition and preparation. As you will see in the pictures, in comparison with last week’s report, more preparation has been done and a...

More

Remodel Week 1

Posted by Daniel Israel on Tuesday, July 28th, 2020 with 1 Comment

Greetings members, friends, and family of EBJI! I imagine that most of these following posts will be short on text, but include photos of the progress. It’s much easier to comprehend the progress being made by seeing the pictures rather than reading the description.  I did a walk-through at the end of the first week...

More

We’re Remodeling!

Posted by Daniel Israel on Monday, July 27th, 2020 with Comments Off on We’re Remodeling!

Greeting to EBJI Members, families, and friends, For more than 20 years now, we’ve been “planning” to remodel the dojo. It’s always been sort of a pipe dream, until a few years back we finally got to the point that (through gifts, investments, and savings) we could afford to actually make it happen! Given that...

More

We’re Offering Virtual Workouts!

Posted by Sayaka Matsumoto on Tuesday, June 9th, 2020 with Comments Off on We’re Offering Virtual Workouts!

Greetings EBJI Members and Families, I hope that you and your families are safe and healthy in these trying times. I wanted to take a moment to reach out and update everybody regarding our schedule and operations. The USJF medical committee is recommending that we cease all activities, so unless we have a change in...

More